Ask two developers to price the same project. One sends a $20,000 fixed quote; the other says “$95 an hour, probably 200 hours or so.” Those look like two prices. They aren’t. They’re two answers to a question neither of them said out loud: who pays when the estimate turns out to be wrong? The fixed quote answers “I do.” The hourly rate answers “you do.” Everything else about the fixed-versus-hourly debate is decoration on top of that one assignment of risk. (Including every agency blog post arguing for whichever model that agency happens to sell.)
§1One question, two answers
The fear on each side of this choice is the same fear wearing different clothes. Hourly buyers fear the running meter: a bill that grows quietly, with no ceiling, invoiced after the fact. Fixed-price buyers fear the padded quote: a number inflated to protect the vendor from their own uncertainty, so you pay for risk that never materializes. Both are the fear of paying for the unknown, and both are rational — because in software the unknown is not a corner case. It’s the main event, and it has been measured.
Both models can be gamed, and knowing how is half the defense. Hourly gets gamed by slowness: gold-plating, “exploring,” a tenth meeting about the third option. Fixed price gets gamed by invisible corners: skipped tests, missing docs, a rushed final week you can’t see from outside. That’s why the pricing model only assigns the risk — the artifacts police the quality. Demos every two weeks, documentation that ships, a warranty with a number on it. A vendor strong on artifacts survives either pricing model. A vendor weak on artifacts will find the leak in whichever one you pick.
So instead of arguing temperament, price the risk like an adult contract would. It happens that the largest software buyer on earth has done exactly that, in writing, for decades.
§2The risk table
The US government buys more software than anyone. Its procurement rulebook, the Federal Acquisition Regulation, is refreshingly blunt about what each pricing model does. On firm fixed price, FAR 16.202-1: it “places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.” On hourly billing, FAR 16.601: a time-and-materials contract “provides no positive profit incentive to the contractor for cost control or labor efficiency.” It may be used “only when it is not possible… to estimate accurately.” That’s the whole debate, settled by the buyer with the most scar tissue:
| The question | Fixed price | Hourly |
|---|---|---|
| Who pays for an overrun? | the developer | you |
| What does a slow week cost the developer? | profit | nothing — it bills |
| Incentive on the estimate | get it right or eat it | keep it optimistic — it’s not binding |
| Where padding hides | in the quote, visible, comparable | in the hours, invisible, after the fact |
| Mid-build changes | need a mechanism (§6) | slide in silently and bill |
| The right deal when… | the work can be scoped | the work genuinely can’t be (§7) |
Read the second row twice, because it’s the one nobody puts in the brochure. Under hourly billing, the developer’s worst outcomes (wrong guesses, rework, meandering) are revenue. Under fixed price they’re losses. Neither model makes anyone a saint. They just point the incentives in opposite directions, and you get to pick which direction points at you. Print the table; it’s the whole debate in six rows, and it fits on an index card.
§3The 27% problem
How often is the estimate wrong? Wrong enough that “who pays for the overrun” should be the first question on any software contract. The best-known numbers come from Bent Flyvbjerg and Alexander Budzier’s study in Harvard Business Review, September 2011. Across 1,471 IT projects, the average cost overrun was 27%. The average is the gentle part. One project in six was what they called a black swan — over budget by 200% on average, and almost 70% over schedule.
My quotes are fixed because the overruns are mine: if milestone three takes twice as long as I estimated, you pay what the quote said.
Their sample skews toward large corporate projects, so read the exact figures as weather from a bigger storm than yours. But the shape of the finding travels to any size: overruns aren’t rare accidents, and the tail is fat. Estimation error isn’t a possibility your contract should mention. It’s a probability your contract should assign, by name, to somebody. When a vendor’s paperwork is silent about overruns, it isn’t because they never happen. It’s because silence assigns them to you.
Put the percentages on a real build to feel them. On a $20,000 project, the average overrun is $5,400 of somebody’s money. The one-in-six tail is a second $40,000 on top of the first $20,000. Under hourly billing you’re exposed to that whole distribution, tail included; under my contract, the distribution is my problem and your exposure is the quote. Estimates skew low for a boring reason — the person estimating is imagining the version of the project where nothing surprises anyone. Assigning the overrun to the estimator is how that person stops imagining and starts checking.
§4The overruns-are-mine clause
Here is the sentence in my contract that this entry is named after, in its plain-language shape:
“The price for each milestone is fixed at quote stage. If the work described in the scope document takes longer than estimated, the price does not change.”
Notice what that does at week five of a build, when something I estimated at three days is entering day seven. Under hourly billing, that moment is a shrug; the meter absorbs it. Under my contract, that moment is mine — my evenings, my margin, my problem, and none of it appears on your invoice. I don’t write about this clause because eating overruns is fun. I write about it because of what it did to my estimates: they got careful, because careless ones cost me directly. FAR calls this “maximum risk” on the contractor, and it is. Risk is exactly what you want the person doing the estimating to hold, because whoever holds it stops guessing.
The obvious comeback deserves its answer: “so you just pad the quote.” Padding is real, and every fixed price on earth contains the vendor’s uncertainty somewhere. The question is whether that uncertainty gets priced by ignorance or by information. A fixed quote written after one phone call has to pad heavily, because the vendor knows almost nothing and charges for everything they don’t know. My quotes are written after a scoping week. The workflows get mapped, the edge cases listed, the “what happens when a job is cancelled mid-route” questions asked before a price exists. Information is the refund on the ignorance tax. That’s the real mechanics of a lean fixed price: not courage, homework.
And the clause’s boundary, stated as plainly as the clause. It covers estimation error — the scope document says X, and X took longer than I guessed. It does not cover scope change: the document says X and you now want Y, which is §6’s territory and gets its own price. Keeping those two separate is most of what the scope document is for. When they blur, every overrun gets renamed a “change” and billed. It’s the oldest trick in the fixed-price playbook, and the first thing §8’s four questions are designed to catch.
§5Where the risk actually goes
A fixed price doesn’t delete estimation risk. It assigns the risk to me, so the structure around it exists to keep it small. Every piece of that structure is visible:
- The scope document. The quote binds to a written description of what “done” means, line by line. It’s the same document the ownership clause points at when it assigns you the “deliverables” — one artifact doing legal and financial work at once.
- Milestones, priced separately. Most projects land between $8,000 and $25,000, fixed at quote stage, split into milestones you approve one at a time. If my estimate on one milestone is wrong, the damage is contained to that milestone. As the continuity entry covers, you own everything you’ve paid for along the way.
- The 6–8 week shape. Most of my builds run 6–8 weeks. Short horizons estimate better than long ones; Flyvbjerg’s black swans live mostly in year-long projects with moving targets. Keeping builds small isn’t just taste. It’s overrun control.
- The demo every two weeks. You see working software mid-build, so a milestone drifting off course is visible in days, not at delivery.
- The 60-day warranty. Bugs I introduced, fixed free, for 60 days after launch. It belongs in this list because a price isn’t really fixed if defects bill separately afterward. The warranty is the part of the quote that survives delivery.
That’s what “fixed price” means here in full: not a brave number, but a system. Scope it, bound it, show it. At the center sits the clause that makes the residual risk mine to carry.
§6How changes get priced
Every fixed-price horror story you’ve heard lives in this section, so here is the mechanism plainly. Mid-build, you’ll want something the scope document doesn’t contain. That’s not a failure; seeing working software creates ideas, and it should. When it happens, the change gets its own small fixed quote, usually a few hundred to a few thousand dollars, priced like a miniature project. You approve it, decline it, or park it for after launch. Nothing bills without a written yes. The scope document grows an appendix instead of a dispute.
The shape of a typical add-on, so you can picture the paperwork: “SMS notification to the customer when a job closes — three days, $900, no impact on milestone four’s date.” Two sentences in an email, a written yes, an appendix line. The decision took a day and left a paper trail; nobody discovers it in an invoice three weeks later. That’s the entire mechanism, and its size is the point.
Both pricing models fail here without a mechanism, in opposite ways. Hourly absorbs changes silently: the bill grows and nobody ever decided anything. Fixed price without a change mechanism turns every new idea into a standoff, which is where the “endless change-request fights” reputation comes from. The mechanism is the fix in both directions — every change is decided, priced, and on paper, and “no” stays a polite complete sentence.
Worth naming: there’s a third respectable answer. 37signals’ Getting Real argues you fix time and budget and flex the scope. Of scope, schedule, and cost, pick two to lock and let the third move. Their pick suits product teams shipping their own software. Mine, scope and price locked with changes queued as add-ons, suits a client buying a defined system with a defined budget. What both reject is the model where nothing is fixed and the meter decides. All three locked is a fantasy; none locked is an invoice with no edges.
§7When hourly is the right deal
FAR’s rule for hourly billing is the fair one: use it when accurate estimation isn’t possible. Real cases exist, and I’d take some of them hourly myself:
- Rescue archaeology. Diagnosing an undocumented system some other developer left behind. Nobody can scope a maze from outside; anyone who quotes it fixed is guessing at your expense or theirs.
- True research. “Can this be done at all?” is not estimable. Timebox it hourly (twenty hours, then a decision) and the meter has a ceiling.
- Ongoing maintenance. A few hours here and there across a year fits hourly or a small monthly agreement fine. There’s nothing to scope; there’s availability. My own care agreements work the same way: a few fixed hours a month, cancelable any month.
- A process still changing monthly. If the target moves, a fixed price binds to a photograph of it. §3 of the keep-renting entry says don’t build at all yet; that advice comes before any pricing model.
If you do rent a meter, rent it with edges. A written ceiling the bill cannot pass without a new decision. Hours reported weekly, not discovered monthly. And a decision point on the calendar where the timebox ends and someone chooses: continue, stop, or convert what’s now known into a fixed quote. Hourly without edges isn’t a pricing model. It’s a subscription to a person.
And one warning about my own side of the table, because fixed price has a vendor-side failure mode too. A desperate vendor can underbid a fixed project, then meet the overrun with the only tools left: cut corners, or walk away mid-build. A suspiciously cheap fixed quote with no scoping artifact behind it isn’t a bargain. It’s the risk coming back to you wearing a discount. The tell is the same one from §4 — ask what the quote binds to. A fixed price with no scope document is just an hourly bill that hasn’t introduced itself yet.
§8The four money questions
Portable version, for any developer or agency, before money moves. Four questions, and what a good answer contains:
- “Who pays if this takes longer than you estimated?” The only clean answers are “I do” with a fixed price, or “you do, so here’s the timebox and the ceiling” with hourly. Watch for the answer that redefines the question into change-request territory. Overruns and changes are different things, and §6 is about keeping them different.
- “What document does the price bind to?” A scope document with a definition of done. “The proposal” is weaker; a proposal describes intentions, a scope document defines completion.
- “How does a mid-build change get priced?” A mechanism: quoted, approved in writing, then built. “We’re flexible” is not a mechanism. It’s a future argument.
- “When do I start owning what I’ve paid for?” Milestone by milestone; the ownership entry unpacks the clause behind it. The question also quietly tests whether the vendor’s payment schedule and their legal paperwork have ever met.
This entry closes a set of three. Who owns the code is the paper. What happens if I disappear is the structure. This one is the money. The three share one design: every promise converts to an artifact you can demand, read, or test before you’ve risked anything. If you want to see where the fixed number comes from, the scoping entry walks through the week that produces it. Sometimes that week ends in “don’t build” — and the quote you never receive is the most honest number I produce.
- FAR 16.202-1 — Firm-fixed-price contracts (US Federal Acquisition Regulation) — www.acquisition.gov/far/16.202-1
- FAR 16.601 — Time-and-materials contracts (US Federal Acquisition Regulation) — www.acquisition.gov/far/16.601
- Flyvbjerg & Budzier — “Why Your IT Project May Be Riskier Than You Think,” Harvard Business Review, September 2011 (1,471 projects; 27% average overrun; 1 in 6 over 200%) — papers.ssrn.com/sol3/papers.cfm?abstract_id=2229735
- 37signals — Getting Real: “Fix Time and Budget, Flex Scope” — basecamp.com/gettingreal/02.4-fix-time-and-budget-flex-scope